Progress continues on converting the former St. Ursuline Center into the new Bayport-Blue Point Public Library. Here’s are some recent developments:
We’re pleased to report that the Library Board has taken several positive steps over the past few months toward converting the former St. Ursuline Center into the new Bayport-Blue Point Library.
Click to view updated drawings for the new library project!
On February 11, 2019 the sale of St. Ursuline convent was completed and the library took ownership of the property at 186 Middle Road; the location of your new library. This is the first step of a multi-step process!
On behalf of the Library Board of Trustees, we would like to extend a sincere thank you to our community for the positive support and passing of the Bayport-Blue Point Library Bond.
Updated Bond Referendum Packet (Nov 30, 2018)
Our community information meeting brought out many of our neighbors and friends on Wednesday evening, October 24, to learn about the library’s proposed building project and bond referendum vote.
The Bayport-Blue Point Library Board is moving ahead with a proposed bond vote on December 6, 2018 to renovate the former St. Ursuline Center for a new library.
In our previous report on the update on the St. Ursula property, we informed the community that the Library Board was in negotiations to try to come to terms on an acquisition price for the St. Ursula property. At this time, we would like to report that we do finally have terms agreed upon for $3,650,000 and will be moving forward with a Public Referendum Vote asking for your approval to acquire and renovate this property into your new and improved community library facility.
In our previous report on the update on the St. Ursula Property, we informed the community that the SEQRA report was finalized and an appraisal was completed for the Library. As this newsletter goes to print, the board continues negotiations with the sellers working to pursue a suitable price for the property.